RE-Tech Delivers Step-Up Solution to Ilmatar Energy’s Joroinen Solar Park
RE-Tech supplied a step-up solution to Ilmatar Energy’s solar park in Joroinen. The client opted for a 4 MVA transformer size. The installation was carried out on a concrete foundation outdoors. In the case of Joroinen, the delivery time for the transformer from design to delivery was 8 months.